Construction activities on the Big Hollow Stream Restoration Project were finally started on August 13, 2001. The project involves full restoration of over 1 mile of stream, and will take several months to complete. The following pictures are of the work in progress, check back often to see the project as it progresses.
D5 Dozer filling old remnant stream channel at lower end of the project reach
D8H & Cat Pan excavating borrow fill from Pond Site #2 channel
Two Terex off-road dump trucks and two Caterpillar pans are being used to haul the estimated 35,000 yards of material required to elevate the stream channel to reconnect with its floodplain
Excavation of pond site #1, material is being used for floodplain fill
D8 & Cat pan being used to cut the new
channel meander through a wooded area.
Constructing a rock-vane just above Peck Road Bridge
Excavation of pond site #2 by excavator and off-road dump truck
Soil & Water Staff performing layout of stream channel and rock structures
Cutting a road off the face of an eroded terrace to reach borrow area
Excavator w/Thumb placing rock structures at lower end of the project
Dozer/Pan & Excavator w/ off-road dumps used to move material from borrow area
Pan traveling up haul road constructed on the face of the steep terrace
Pan traveling haul road constructed on the face of the steep terrace, looking down slope
Pan being used to excavate new channel planform as it passes through the woods
GCSWCD Staff laying out Rock Vane for construction
Delivery of large rock for Rock and Cross Vanes. Loads 35-45 tons each
Completed Rock Vane with scour hole
excavated downstream
Work proceeds on lower Cross Vane near Peck Road bridge
Excavator working on Rock Vane just upstream from Peck Road Bridge